Tiorco & Nalco

i2 Construction was the negotiated general contractor on the relocation of Tiorco’s World Headquarters and Petroleum Testing Laboratory to Denver, Colorado. The project included 7K SF of office and a 10K SF state-of-the-art laboratory. The successful completion of this project also led to an additional negotiated expansion to Tiorco’s office, this time with Gensler as the A/E resource in 2010, as well as another office and Petroleum Testing Laboratory remodel for Tiorco and parent company Nalco Stepan that was completed in 2014.

Preliminary budget on the initial relocation, accomplished from 30% schematic designs and M/E/P narratives, indicated that as designed, the project would fall outside of the budget parameters set by Tiorco’s parent company. i2 Construction worked with the design team and client to value engineer the project so that when competitively bid, the project fell within the budget requirements of the client.